
Max hourly regasification rate (m3/h) – the maximum amount of LNG that can be regasified within one hour.
Working days per gas year – the number of working days of the terminal in the gas year, excluding the maintenance days.
Yearly send-out (m3) – the maximum amount of gas that can be delivered to the transmission system in a gas year.
Maximum capacity – the maximum regasification capacity of LNG given the technical characteristics of the LNG terminal.
Technical capacity – the maximum regasification capacity of LNG given the technical characteristics of the LNG terminal, the technical possibilities of the transmission system and the other factors.
Commercial capacity – the maximum regasification capacity of LNG available for allocation to terminal users.