Under the Government of the Republic of Croatia’s decision to increase the security of gas supply through the construction of the Zlobin—Bosiljevo gas pipeline and increase the capacity of the LNG Terminal to 6.1 billion cubic meters of gas per year, the company LNG Hrvatska d.o.o., as the operator of the LNG Terminal, is in charge of the project to increase the capacity of the LNG Terminal.

Installing an additional regasification module and the accompanying equipment necessary for safe and reliable LNG regasification and natural gas transmission from the FSRU vessel LNG Croatia will increase the LNG terminal’s capacity.

Given the specific requirements of the regasification module, which must adhere to high standards of environmental protection, all equipment installed in the module, as well as the equipment added for the implementation of the new regasification module in the existing system, must comply with stringent environmental and technical standards.

Main job description:

  1. Design, procurement, installation, and implementation of an additional regasification module with a maximum natural gas send-out capacity of 250,000 mᵌ/h
  2. Design, procurement, and installation of a seawater pump for the needs of seawater supply for an additional regasification module
  3. Design, procurement, and installation of seawater filters for seawater purification for an additional regasification module
  4. Design and modification of the FSRU control system of the LNG Croatia vessel